Electricity crisis in Sonepat: First the box burst, then the fault in the underground cable, half the town was in darkness for 18 hours

news2news

Electricity crisis in Sonepat: First the box burst, then the fault in the underground cable, half the town was in darkness for 18 hours

Sonipat News:Line Par’s Old Rohtak Road area was plunged into darkness all night. Power remained cut in more than two dozen colonies in the area. After about 18 hours, the power supply was restored, even from the old line. The fault of the new subway line could not be found at all. So it happened that late at night the supply box from Electricity Corporation 33kVA substation to the industrial area burst, after that the box was repaired somehow, then destroyed the underground power supply from the substation to 11KV power station in the industrial area Wire breakage occurred. After an intensive search for the bug, the bug was also found, but it could not be fixed until the message was written late Wednesday evening. Although Gurugram’s team was called in to fix it. For this reason, the power supply from the old line was started late in the evening.

Let us inform you that around 2am the power box leading from the 33kVA substation of the municipal electric company to the industrial area had exploded. As a result, there was no electricity all night. When the box was repaired in the morning, two of the 4 underground cables that were laid to power the 11 kV power station found a fault in the cable route. For this reason, the power supply to the 11 kV power station was discontinued. The Electricity Corporation team began troubleshooting. Somehow a fault in two power cables was discovered in the afternoon on a block near ITI Chowk. Meanwhile, the rain also disrupted the work. If the power line fault could not be fixed by late evening, a team from Gurugram was called in to fix it. This error could not be corrected until the message was written.

This area remained affected, blackout for 18 hours

Because of this blackout, more than two dozen colonies in the Old Rohtak Road area across the line experienced a power outage lasting more than 18 hours. Vishal Nagar, Dev Nagar, Mission Chowk Road, Purani Mandi, Kat Mandi, West Ramnagar, Ram Nagar, Brahma Nagar, Suri Petrol Pump Wali Gali, Pathar Wali Gali, Rohtak Road, Arya Nagar, Kalupur, Bhagat Singh Colony, Mirch Mandi, Many other areas including Biyapur, Laharada, Kalupur Chungi, Baba Colony and Mohan Nagar have been without power since late Tuesday night which started late Wednesday night. People faced many problems due to the power outage. First of all, the drinking water supply could not be found, it prided itself on the fact that the weather remained cool, which reduced water consumption and people’s work continued. Otherwise people’s problems could have ended up on the streets.

Old line started, load laid after 2 hours

The special team reached Sonepat from Gurugram on Wednesday afternoon. Using modern machines, the team found the error. But meanwhile it started to rain heavily. Because of this, the underground cable line was flooded. Given the circumstances, the team that arrived to repair the underground fault decided to wait before starting work. In such a situation, Electricity Corporation had to make the decision to take power over the old line.

Late in the night a box burst from the powerhouse, after its repair the power supply was put into operation. Then there was a fault in the underground cable. Cable fault was found, work is being done to fix it. The old line was restarted to restore power. The supply from the new line only takes place after the fault in the new line has been rectified; before that, an attempt is made to start supply from the old line. ,Vicky Gehlawat, SDO, Sonepat

Also read this – Gift to Sonipat: Deputy CM Dushyant Chautala said – 80 percent of wheat cultivation in the state completed